MISO must boost transparency on Entergy grid: stakeholders
Houston (Platts)--22Feb2013/328 pm EST/2028 GMT
Stakeholders in the Entergy footprint want more transparency in reports
from the new independent coordinator of transmission, Entergy Regional State
Committee members learned Friday.
The Midwest Independent Transmission System Operator became the ICT for
the Entergy footprint in December.
During an ERSC meeting held in New Orleans and available by phone and
online, a MISO representative reported that transmission service was
curtailed for 1,110 hours in January, compared with 818 hours in December.
Previous ICT metrics reports show transmission service had to be curtailed
1,184 hours in January 2012.
Article continues below...
|
|
Sign up for Megawatt Daily
|
|
|
Megawatt Daily provides detailed coverage of power prices in major US and Canadian electricity markets, up-to-date information about solicitations and supply deals, and information about complex state and federal power regulations.
|
|
Entergy curtailed 85.3 million MWh in January, compared with 5.1 million
MWh in December and 66 million MWh in January 2012.
In explaining why the January curtailments were more than December, the
representative said December was warmer than usual and January was cooler,
and the Entergy system had an unexpected forced outage.
But that was not a sufficient explanation, said Jennifer Vosburg,
president of NRG Energy's Louisiana Generating facility, who chairs the ICT
Stakeholders Committee.
"Telling us it was cold in January is not a satisfactory answer," she
said.
MISO took over the ICT function from Southwest Power Pool, which had
included discussion of which transmission constraints contributed to
curtailments.
"It's not just about the numbers, it's about the analysis and how do we
fix it," she said.
Brandon Presley, a Mississippi Public Service Commission member and ERSC
vice president, agreed that such details were useful. Presley chaired
Friday's meeting in the absence of ERSC President Ken Anderson, a Public
Utility Commission of Texas member.
Regulatory bodies from Arkansas, Louisiana, Mississippi, New Orleans and
Texas comprise the ERSC, because each of those states oversees Entergy
operating companies.
The MISO speaker said the ICT would include such information in future
reports.
A presentation by Robert Sinclair, of Potomac Economics, which serves as
the ICT independent market monitor, showed that Entergy acquired generation
capacity through the weekly procurement process in only two of the five weeks
ending February 16.
During the other three weeks, Entergy did not acquire capacity because a
"hold harmless" provision under the Federal Energy Regulatory
Commission-ordered ICT arrangement states that the New Orleans-based
investor-owned utility need not acquire power when Entergy's legacy
generation is expected to be less expensive than WPP procurements, Sinclair
said.
But out of the 11 weeks during which MISO has been ICT, the WPP
suppliers' costs would have been less than the Entergy cost in three of the
four times the hold harmless provision was invoked. Potomac Economics is
"evaluating the underlying conditions that may explain the hold harmless
instances," Sinclair said.
Entergy has petitioned state and federal regulators to join MISO and to
sell off its transmission grid to a new entity owned by ITC Holdings, of
which Entergy shareholders would own 50.1%.
The ERSC learned that local balancing authorities, which are entities
responsible for regulating the grid at 60 hertz, are to submit by March 1
their network models to MISO, which will serve as the Entergy footprint's
central balancing authority. Also, MISO is conducting new member outreach and
market training.
--Mark Watson, markham_watson@platts.com
--Edited by Lisa Miller, lisa_miller@platts.com