Fukushima panel told some details will take five years to learn
Washington (Platts)--7Sep2012/452 am EDT/852 GMT
Key details of how the accident at Japan's Fukushima I nuclear plant
played out have yet to be determined and may not be known for five years or
more, when important parts of the plant are safer to enter, officials with
the Japanese and US nuclear industries told a US National Academies review
committee Thursday.
A committee of the National Academies is conducting the study, which is
mandated by Congress, on behalf of the US Nuclear Regulatory Commission. The
committee held its second data-gathering session Thursday in Washington. The
panel was established in March and information-gathering will continue
through 2013, committee chairman Norman Neureiter said at the meeting.
A report to NRC and Congress is expected to be delivered in April 2014,
Neureiter said.
Article continues below...
|
| Request a free trial of: Power in Asia |  |
 | Power in Asia is a fortnightly newsletter that provides incisive comment and analysis on the policies and projects that shape the electricity market in Asia. You will receive information on corporate activity and performance, utility strategy and trends plus country-by-country news, market commentary, statistics and results.
|
|
Officials with Tokyo Electric Power Co., owner and operator of the
Fukushima I plant, discussed the accident with committee members, saying that
in hindsight, tsunami protection measures at the site were inadequate. The
protection level was set at 3.1 meters (10.2 feet) above sea level when the
plant was originally permitted in 1966, but that was raised to 5.7 meters in
2002, Tepco said in a presentation.
However, the tsunami on March 11, 2011 reached an estimated height of
more than 14 meters, overwhelming the station's electrical distribution
system and leading to a complete loss of power at four of the six nuclear
units. Three of those units experienced melting of all or most of their
nuclear fuel, resulting in explosions and radiation releases in the days
following the tsunami.
A Japanese civil engineering society had discounted the possibility of a
large earthquake and tsunami off the coast of Fukushima prefecture because of
a lack of evidence of such events since the 17th century, Tepco manager Shin
Takizawa said. A study in 2002 that suggested such an earthquake was
possible and historical reports of a large tsunami in the area in the ninth
century were under review at the time of the 2011 earthquake, but had not
been confirmed, he said.
"In hindsight, if we were able to return to 2002 ... we would have taken
different actions," Takizawa said.
An official with the Institute for Nuclear Power Operations, a US
industry group set up to promote nuclear safety after the partial meltdown of
a unit at Three Mile Island in 1979, said while the sequence of events at
Fukushima following the earthquake is becoming increasingly clear, some
details will take several years to learn. INPO produced a report in November
providing a minute-by-minute description of events at the Fukushima units.
Steve Meng, manager of emergency preparedness for INPO, said that study
showed the difficult circumstances under which Fukushima workers found
themselves, without emergency lighting, critical instrument readings and
power to operate valves, along with increasing radiation levels and a
series of explosions as time went on. The first explosion, which damaged
equipment that was being installed to provide emergency power, was "one of
the key turning points for the event," Meng said.
The nuclear industry expects to learn "quite a bit more" about the
accident in the next five or more years, INPO senior vice president Bill
Webster told the committee. Information about the position of valves in a key
cooling system and other details from within the reactor building will be
discovered when those areas are safe to enter, he said.
Yasunori Yamanaka, manager of Tepco's nuclear safety engineering group,
said following the meeting that one of the key pieces of information that
will be learned in the coming years is the location and condition of the core
of nuclear fuel in the three reactors that experienced meltdowns. Tepco
believes the uranium fuel of unit 1 at Fukushima I almost entirely melted its
way through the bottom of the thick steel reactor vessel and poured to the
floor of the containment structure, eating through a portion of the concrete
floor of that area.
The company plans to use cameras and other surveillance equipment to
determine how much of the core of units 2 and 3 remain in the reactor,
Yamanaka said. The company believes almost half of the fuel in those units,
which maintained core cooling longer, melted, he said. It may take more than
five years before Tepco can determine whether the fuel in those units remains
in the bottom of the reactor vessel or also fell to the containment floor,
Yamanaka said.
--William Freebairn, william_freebairn@platts.com
--Edited by Lisa Miller, lisa_miller@platts.com