Exelon Illinois nuclear units at 100% after output cuts requested by PJM

Washington (Platts)--27 Oct 2017 446 pm EDT/2046 GMT


Five Exelon Generation nuclear units in Illinois have returned to full-power operation after reducing their output late Thursday night and early Friday morning at the request of regional transmission operator PJM Interconnection, according to a company spokeswoman.

The 912-MW Quad Cities-1 and 994-MW Quad Cities-2 in Cordova, Illinois, reduced output beginning at 11:40 pm CDT Thursday (0440 GMT Friday) "in coordination with PJM due to pricing signals and transmission line constraints," Exelon spokeswoman Dorothy Wallheimer said in an email Friday.

Related Snapshot video:US uranium producers plagued by low prices, scant utility purchasing

Both units were operating at 100% of capacity as of 4:20 am CDT (920 GMT), Wallheimer said. Earlier that morning, unit 1 was operating at 93% and unit 2 at 94%, the US Nuclear Regulatory Commission said in its daily reactor status report.

The 1,268-MW Byron-1 in Byron, Illinois, reduced output for the same reason beginning at 11:55 pm CDT Thursday (0455 GMT Friday) and was operating at 100% as of 9:30 am CDT (1430 GMT) Friday, Wallheimer said. Earlier that morning, the unit was operating at 95% of capacity, NRC said in its report.

Article continues below...


Request a free trial of: Nucleonics WeekNucleonics Week
Nucleonics Week

Since 1960, Platts Nucleonics Week has been the leading source of global news for the commercial nuclear power business. Nucleonics Week delivers analysis with a depth and sophistication simply unavailable anywhere else.

Request a free trialMore Information


The 1,320-MW Braidwood-1 and the 1,295-MW Braidwood-2 in Braceville, Illinois, reduced output for the same reason beginning at 12:12 am CDT (0512 GMT) Friday, and both units were operating at 100% as of 8:30 am CDT (1330 GMT) that day, Wallheimer said. Earlier that morning, both units were operating at 98% of capacity, according to NRC's report.

Since 2015, Exelon has temporarily reduced off-peak output at one or more of its nuclear plants in Illinois numerous times in coordination with PJM because of grid constraints and what the company calls "pricing signals."

Exelon has previously said intermittent grid congestion has been occurring in the region around those plants because of transmission line outages for scheduled maintenance, large influxes of wind-generated power into the grid during off-peak hours, or a combination of those factors.

--Steven Dolley, steven.dolley@spglobal.com

--Edited by Derek Sands, derek.sands@spglobal.com



Related News & Analysis


News features Video archives Commodities Spotlight podcast archive

Related Products & Events


Nucleonics Week Financing US Power, 17th Annual

Copyright © 2018 S&P Global Platts, a division of S&P Global. All rights reserved.